User Tools

Site Tools


beamtimes:2024:timeplan

This is an old revision of the document!


Timeplan for Setup in the A1-Hall

The goal is to have a fully equipped and running detector in A1 at October 16th.

**First commissioning beam time: 16.10.-27.10.**

To do in HIM hall:

  • [x] Cable the detector (P, C, S, Aj) (30.08.)
  • [x] detector submodule position measurement (P+C+S) (06.09.)
  • [x] leakage test, test at room temperature (J+P) (06.09.)
  • [x] splitter board test (L) (06.09.)
  • [ ] VLAN commissioning (L) (24.09.)
  • [x] humidity test (J+P) (17.09.)
  • [x] cool the detector (18.09.)
  • [x] cable the rack (O+L) (18.09.)
  • [x] assemble SADC setup (O+A) (13.09.)
  • [x] HV control (18.09.)
  • [x] read out commercial sensors with keysight (20.09.)
  • [-] read out and control whole detector at once (20.09.)
  • [-] cosmic measurement 200MeV; warm or cold? (23.09.)
  • [ ] build cable pocket (23.09.)
  • [x] test run with stapler
  • [ ] Get cabled detector ready for movement (24.09.)
  • [ ] get chiller ready (27.09.)
  • [ ] get racks ready (25.09.)

Time plan in A1-hall:

  • [x] Move spectrometers (30.08.)
  • [x] Clear stuff in A1 hall (S) (30.08.)
  • [x] Disassemble exit beam pipe (29.08. 10 o'clock)
  • [x] Disassemble target chamber (06.09.)
  • [x] Build, install and measure target ladder
  • [x] install new target chamber
  • [x] Build MayTech table in A1-Hall (10.09.)
  • [ ] Build detector frame and adjust feet (24.09.)
  • [ ] Move calorimeter to A1-Hall (25.09.)
  • [ ] Install calorimeter with exit beam pipe (25.09.)
  • [x] Close target chamber and vacuum test (24.09.)
  • [ ] Install infrastructure (PC, Racks, etc.) (26.09.)
  • [ ] cable calormeter on rack side (priority: signal cables and LV, then: light pulser and HV) (27.09.)
  • [ ] Align and measure calorimeter (02.10.)
  • [ ] install VAT and window and flange (09.10.)
  • [ ] read out and control whole detector at once (04.10.)
  • [ ] Cool detector (04.10.)
  • [ ] Vacuum test of exit beampipe ?
  • [ ] Put vacuum on exit beampipe for beamtime (14.10.)
  • [ ] Cosmic measurement, 25 MeV, cold (16.10.)
  • [ ] install more nests, which are visible from the sides ?

Counting room:

  • [ ] network
  • [ ] server
  • [ ] computers etc.

Cooling (J):

  • [x] connect outer cooling (06.09.)
  • [x] prepare manifold boxes
  • [x] humidity readout (10.09.)

Parts Missing:

  • VAT holding structure
  • scintillators, read out by PMTs; up to six
beamtimes/2024/timeplan.1727096128.txt.gz · Last modified: 2024/09/23 12:55 by himuser

Donate Powered by PHP Valid HTML5 Valid CSS Driven by DokuWiki