Timeplan for Setup in the A1-Hall
The goal is to have a fully equipped and running detector in A1 at October 16th.
**Firs commissioning beam time: 16.10.-27.10.**
To do in HIM hall:
- [x] Cable the detector (P, C, S, Aj) (30.08.)
- [x] detector submodule position measurement (P+C+S) (06.09.)
- [ ] leakage test, humidity test at room temperature or 10 deg (J+P) (06.09.)
- [ ] splitter board test (L) (06.09.)
- [ ] VLAN commissioning (O) (06.09.)
- [x] assemble SADC setup (O+A) (13.09.)
- [ ] read out whole detector at once (13.09.)
- [ ] cosmic measurement 200MeV; warm or cold? (13.09.)
- [ ] build cable pocket
- [ ] install more nests, which are visible from the sides
- [ ] Get cabled detector ready for movement (16.09.)
Time plan in A1-hall:
- [x] Move spectrometers (30.08.)
- [x] Clear stuff in A1 hall (S) (30.08.)
- [x] Disassemble exit beam pipe (29.08. 10 o'clock)
- [x] Disassemble target chamber (06.09.)
- [x] Build, install and measure target ladder
- [x] install new target chamber
- [ ] Build MayTech table in A1-Hall (10.09.)
- [ ] Move calorimeter to A1-Hall (17.09.)
- [ ] Close target chamber and vacuum test (20.09.)
- [ ] Install calorimeter (17.09.)
- [ ] Align and measure calorimeter (20.09.)
- [ ] Install exit beam pipe (04.10.)
- [ ] Vacuum test of exit beampipe
- [ ] Install infrastructure (PC, Racks, etc.) (04.10.)
- [ ] Cable calorimeter on Rack side (04.10.)
- [ ] Test all submodules (11.10.)
- [ ] Put vacuum on exit beampipe for beamtime (14.10.)
- [ ] Cool detector (14.10.)
- [ ] Cosmic measurement, 25 MeV, cold
Cooling (J):
- [ ] connect outer cooling (06.09.)
- [x] prepare manifold boxes
- [ ] humidity readout
Parts Missing:
- temperature cables external
- adapter plates for table (feet, rails, etc.)
- “Belegbretter” for table
- finish flange for exit beam pipe downstream
- central alignment piece for calorimeter