Timeplan for Setup in the A1-Hall
The goal is to have a fully equipped and running detector in A1 at October 18th.
To do in HIM hall:
- [ ] Cable the detector (P, C, S, Aj) (30.08.)
- [ ] detector submodule position measurement (P+C+S) (06.09.)
- [ ] leakage test, humidity test at room temperature or 10 deg (J+P) (06.09.)
- [ ] splitter board test (06.09.)
- [ ] VLAN commissioning (06.09.)
- [ ] assemble SADC setup (13.09.)
- [ ] read out whole detector at once (13.09.)
- [ ] cosmic measurement 200MeV; warm or cold? (16.09.)
Time plan in A1-hall:
- [x] Move spectrometers (30.08.)
- [ ] Clear stuff in A1 hall (S) (30.08.)
- [ ] Disassemble exit beam pipe (29.08. 10 o'clock)
- [ ] Disassemble target chamber (06.09.)
- [ ] Build MayTech table in A1-Hall (10.09.)
- [ ] Install new target chamber (13.09.)
- [ ] Install exit beam pipe and calorimeter (20.09.)
- [ ] Cable calorimeter (27.09.)
- [ ] Install infrastructure (PC, Racks, etc.) (04.10.)
- [ ] Test all submodules (11.10.)
- [ ] Cool detector (18.10.)
Cooling (J):
- [ ] connect outer cooling (06.09.)
- [ ] dry air module readout via LAN (Pierre)
- [ ] prepare manifold boxes
- [ ] humidity readout
What else:
- detector position measurement in A1 hall
- Targets
- Vacuum tests
Parts Missing:
- temperature cables extern
- USBC cables for half subunits
- cooling connectors
- cooling box
- adapter plates for table (feet, rails, etc.)
- Belegbretter
- flange for exit beam pipe