Timeplan for Setup in the A1-Hall

The goal is to have a fully equipped and running detector in A1 at October 18th.

To do in HIM hall:

  • [ ] Cable the detector
  • [ ] leakage test, humidity test at room temperature or 10 deg (30.08.)

Time plan in A1-hall:

  • [ ] Move spectrometers (30.08.)
  • [ ] Disassemble exit beam pipe (30.08.)
  • [ ] Disassemble target chamber (06.09.)
  • [ ] Build MayTech table in A1-Hall (10.09.)
  • [ ] Install new target chamber (13.09.)
  • [ ] Install exit beam pipe and calorimeter (20.09.)
  • [ ] Cable calorimeter (27.09.)
  • [ ] Install infrastructure (PC, Racks, etc.) (04.10.)
  • [ ] Test all submodules (11.10.)
  • [ ] Cool detector (18.10.)

What else:

  • detector submodule position measurement
  • detector position measurement in A1 hall
  • Targets
  • Vacuum tests

Parts Missing:

  • temperature cables intern and extern
  • cooling connectors
  • cooling box
  • adapter plates for table (feet, rails, etc.)
  • Belegbretter
  • flange for exit beam pipe