Timeplan for Setup in the A1-Hall
The goal is to have a fully equipped and running detector in A1 at October 18th.
To do in HIM hall:
- [ ] Cable the detector
- [ ] leakage test, humidity test at room temperature or 10 deg (30.08.)
Time plan in A1-hall:
- [ ] Move spectrometers (30.08.)
- [ ] Disassemble exit beam pipe (30.08.)
- [ ] Disassemble target chamber (06.09.)
- [ ] Build MayTech table in A1-Hall (10.09.)
- [ ] Install new target chamber (13.09.)
- [ ] Install exit beam pipe and calorimeter (20.09.)
- [ ] Cable calorimeter (27.09.)
- [ ] Install infrastructure (PC, Racks, etc.) (04.10.)
- [ ] Test all submodules (11.10.)
- [ ] Cool detector (18.10.)
What else:
- detector submodule position measurement
- detector position measurement in A1 hall
- Targets
- Vacuum tests
Parts Missing:
- temperature cables intern and extern
- cooling connectors
- cooling box
- adapter plates for table (feet, rails, etc.)
- Belegbretter
- flange for exit beam pipe