Timeplan for Setup in the A1-Hall

The goal is to have a fully equipped and running detector in A1 at October 16th.

**First commissioning beam time: 16.10.-27.10.**

To do in HIM hall:

  • [x] Cable the detector (P, C, S, Aj) (30.08.)
  • [x] detector submodule position measurement (P+C+S) (06.09.)
  • [x] leakage test, test at room temperature (J+P) (06.09.)
  • [x] splitter board test (L) (06.09.)
  • [x] humidity test (J+P) (17.09.)
  • [x] cool the detector (18.09.)
  • [x] cable the rack (O+L) (18.09.)
  • [x] assemble SADC setup (O+A) (13.09.)
  • [x] HV control (18.09.)
  • [x] read out commercial sensors with keysight (20.09.)
  • [-] read out and control whole detector at once (20.09.)
  • [-] cosmic measurement 200MeV; warm or cold? (23.09.)
  • [x] build cable pocket (23.09.)
  • [ ] VLAN commissioning (L) (24.09.)
  • [x] test run with stapler
  • [x] Get cabled detector ready for movement (24.09.)
  • [x] get racks ready (25.09.)
  • [x] get chiller ready (27.09.)

Time plan in A1-hall:

  • [x] move spectrometers (30.08.)
  • [x] clear stuff in A1 hall (S) (30.08.)
  • [x] disassemble exit beam pipe (29.08. 10 o'clock)
  • [x] disassemble target chamber (06.09.)
  • [x] build, install and measure target ladder
  • [x] install new target chamber
  • [x] build MayTech table in A1-Hall (10.09.)
  • [x] close target chamber and vacuum test (24.09.)
  • [x] build detector frame and adjust feet (24.09.)
  • [x] move calorimeter to A1-Hall (25.09.)
  • [x] install calorimeter with exit beam pipe (25.09.)
  • [x] Install infrastructure (PC, Racks, etc.) (26.09.)
  • [ ] cable calorimeter on rack side (priority: signal cables and LV, then: light pulser and HV) (04.10.)
  • [ ] install chiller and dry air (04.10.)
  • [ ] build lead wall for chiller (11.10)
  • [ ] biuld holding structure for VAT valve
  • [ ] scintillator-pmt readout with VME crate
  • [ ] holding structure for PMTs
  • [ ] align and measure calorimeter (02.10.)
  • [ ] read out and control whole detector at once (04.10.)
  • [ ] cool detector (07.10.)
  • [ ] install VAT and window and flange (09.10.)
  • [ ] vacuum test of exit beampipe ?
  • [ ] put vacuum on exit beampipe for beamtime (14.10.)
  • [ ] cosmic measurement, 25 MeV, cold (16.10.)
  • [ ] install more nests, which are visible from the sides ?

Scintillators:

  • [ ] find 6 scintillators with PMTs
  • [ ] HV with VME crate
  • [ ] read out signal with VME crate (which module?)
  • [ ] holding structure

Counting room:

  • [ ] network
  • [ ] server
  • [ ] computers etc.

Cooling (J):

  • [x] connect outer cooling (06.09.)
  • [x] prepare manifold boxes
  • [x] humidity readout (10.09.)

Parts Missing:

  • VAT holding structure
  • scintillators, read out by PMTs; up to six