[x] Cable the detector (P, C, S, Aj) (30.08.)
[x] detector submodule position measurement (P+C+S) (06.09.)
[x] leakage test, test at room temperature (J+P) (06.09.)
[x] splitter board test (L) (06.09.)
[x] humidity test (J+P) (17.09.)
[x] cool the detector (18.09.)
[x] cable the rack (O+L) (18.09.)
[x] assemble SADC setup (O+A) (13.09.)
[x] HV control (18.09.)
[x] read out commercial sensors with keysight (20.09.)
[-] read out and control whole detector at once (20.09.)
[-] cosmic measurement 200MeV; warm or cold? (23.09.)
[x] build cable pocket (23.09.)
[ ] VLAN commissioning (L) (24.09.)
[x] test run with stapler
[x] Get cabled detector ready for movement (24.09.)
[x] get racks ready (25.09.)
[x] get chiller ready (27.09.)
[x] move spectrometers (30.08.)
[x] clear stuff in A1 hall (S) (30.08.)
[x] disassemble exit beam pipe (29.08. 10 o'clock)
[x] disassemble target chamber (06.09.)
[x] build, install and measure target ladder
[x] install new target chamber
[x] build MayTech table in A1-Hall (10.09.)
[x] close target chamber and vacuum test (24.09.)
[x] build detector frame and adjust feet (24.09.)
[x] move calorimeter to A1-Hall (25.09.)
[x] install calorimeter with exit beam pipe (25.09.)
[x] Install infrastructure (PC, Racks, etc.) (26.09.)
[ ] cable calorimeter on rack side (priority: signal cables and LV, then: light pulser and HV) (04.10.)
[ ] install chiller and dry air (04.10.)
[ ] build lead wall for chiller (11.10)
[ ] biuld holding structure for VAT valve
[ ] scintillator-pmt readout with VME crate
[ ] holding structure for PMTs
[ ] align and measure calorimeter (02.10.)
[ ] read out and control whole detector at once (04.10.)
[ ] cool detector (07.10.)
[ ] install VAT and window and flange (09.10.)
[ ] vacuum test of exit beampipe ?
[ ] put vacuum on exit beampipe for beamtime (14.10.)
[ ] cosmic measurement, 25 MeV, cold (16.10.)
[ ] install more nests, which are visible from the sides ?