====== Timeplan for Setup in the A1-Hall ====== The goal is to have a fully equipped and running detector in A1 at October **16th**. === **First commissioning beam time: 16.10.-27.10.** === To do in HIM hall: * [x] Cable the detector (P, C, S, Aj) (30.08.) * [x] detector submodule position measurement (P+C+S) (06.09.) * [x] leakage test, test at room temperature (J+P) (06.09.) * [x] splitter board test (L) (06.09.) * [x] humidity test (J+P) (17.09.) * [x] cool the detector (18.09.) * [x] cable the rack (O+L) (18.09.) * [x] assemble SADC setup (O+A) (13.09.) * [x] HV control (18.09.) * [x] read out commercial sensors with keysight (20.09.) * [-] read out and control whole detector at once (20.09.) * [-] cosmic measurement 200MeV; warm or cold? (23.09.) * [x] build cable pocket (23.09.) * [ ] VLAN commissioning (L) (24.09.) * [x] test run with stapler * [x] Get cabled detector ready for movement (24.09.) * [x] get racks ready (25.09.) * [x] get chiller ready (27.09.) Time plan in A1-hall: * [x] move spectrometers (30.08.) * [x] clear stuff in A1 hall (S) (30.08.) * [x] disassemble exit beam pipe (29.08. 10 o'clock) * [x] disassemble target chamber (06.09.) * [x] build, install and measure target ladder * [x] install new target chamber * [x] build MayTech table in A1-Hall (10.09.) * [x] close target chamber and vacuum test (24.09.) * [x] build detector frame and adjust feet (24.09.) * [x] move calorimeter to A1-Hall (25.09.) * [x] install calorimeter with exit beam pipe (25.09.) * [x] Install infrastructure (PC, Racks, etc.) (26.09.) * [ ] cable calorimeter on rack side (priority: signal cables and LV, then: light pulser and HV) (04.10.) * [ ] install chiller and dry air (04.10.) * [ ] build lead wall for chiller (11.10) * [ ] biuld holding structure for VAT valve * [ ] scintillator-pmt readout with VME crate * [ ] holding structure for PMTs * [ ] align and measure calorimeter (02.10.) * [ ] read out and control whole detector at once (04.10.) * [ ] cool detector (07.10.) * [ ] install VAT and window and flange (09.10.) * [ ] vacuum test of exit beampipe ? * [ ] put vacuum on exit beampipe for beamtime (14.10.) * [ ] cosmic measurement, 25 MeV, cold (16.10.) * [ ] install more nests, which are visible from the sides ? Scintillators: * [ ] find 6 scintillators with PMTs * [ ] HV with VME crate * [ ] read out signal with VME crate (which module?) * [ ] holding structure Counting room: * [ ] network * [ ] server * [ ] computers etc. Cooling (J): * [x] connect outer cooling (06.09.) * [x] prepare manifold boxes * [x] humidity readout (10.09.) Parts Missing: * VAT holding structure * scintillators, read out by PMTs; up to six