beamtimes:2024:timeplan [2024/09/23 13:10] – himuser | beamtimes:2024:timeplan [2024/09/30 12:03] (current) – himuser | ||
---|---|---|---|
Line 18: | Line 18: | ||
* [-] read out and control whole detector at once (20.09.) | * [-] read out and control whole detector at once (20.09.) | ||
* [-] cosmic measurement 200MeV; warm or cold? (23.09.) | * [-] cosmic measurement 200MeV; warm or cold? (23.09.) | ||
- | * [ ] build cable pocket (23.09.) | + | * [x] build cable pocket (23.09.) |
* [ ] VLAN commissioning (L) (24.09.) | * [ ] VLAN commissioning (L) (24.09.) | ||
* [x] test run with stapler | * [x] test run with stapler | ||
- | * [ ] Get cabled detector ready for movement (24.09.) | + | * [x] Get cabled detector ready for movement (24.09.) |
- | * [ ] get racks ready (25.09.) | + | * [x] get racks ready (25.09.) |
- | * [ ] get chiller ready (27.09.) | + | * [x] get chiller ready (27.09.) |
Line 36: | Line 36: | ||
* [x] build MayTech table in A1-Hall (10.09.) | * [x] build MayTech table in A1-Hall (10.09.) | ||
* [x] close target chamber and vacuum test (24.09.) | * [x] close target chamber and vacuum test (24.09.) | ||
- | * [ ] build detector frame and adjust feet (24.09.) | + | * [x] build detector frame and adjust feet (24.09.) |
- | * [ ] move calorimeter to A1-Hall (25.09.) | + | * [x] move calorimeter to A1-Hall (25.09.) |
- | * [ ] install calorimeter with exit beam pipe (25.09.) | + | * [x] install calorimeter with exit beam pipe (25.09.) |
- | * [ ] Install infrastructure (PC, Racks, etc.) (26.09.) | + | * [x] Install infrastructure (PC, Racks, etc.) (26.09.) |
- | * [ ] cable calorimeter on rack side (priority: signal cables and LV, then: light pulser and HV) (27.09.) | + | * [ ] cable calorimeter on rack side (priority: signal cables and LV, then: light pulser and HV) (04.10.) |
+ | * [ ] install chiller and dry air (04.10.) | ||
+ | * [ ] build lead wall for chiller (11.10) | ||
+ | * [ ] biuld holding structure for VAT valve | ||
+ | * [ ] scintillator-pmt readout with VME crate | ||
+ | * [ ] holding structure for PMTs | ||
* [ ] align and measure calorimeter (02.10.) | * [ ] align and measure calorimeter (02.10.) | ||
* [ ] read out and control whole detector at once (04.10.) | * [ ] read out and control whole detector at once (04.10.) | ||
- | * [ ] cool detector (04.10.) | + | * [ ] cool detector (07.10.) |
* [ ] install VAT and window and flange (09.10.) | * [ ] install VAT and window and flange (09.10.) | ||
* [ ] vacuum test of exit beampipe ? | * [ ] vacuum test of exit beampipe ? |