Line 10: Line 10:
   * [x] leakage test, test at room temperature (J+P) (06.09.)   * [x] leakage test, test at room temperature (J+P) (06.09.)
   * [x] splitter board test (L) (06.09.)   * [x] splitter board test (L) (06.09.)
-  * [ ] VLAN commissioning (L) (24.09.) 
   * [x] humidity test (J+P) (17.09.)   * [x] humidity test (J+P) (17.09.)
   * [x] cool the detector (18.09.)   * [x] cool the detector (18.09.)
Line 19: Line 18:
   * [-] read out and control whole detector at once (20.09.)   * [-] read out and control whole detector at once (20.09.)
   * [-] cosmic measurement 200MeV; warm or cold? (23.09.)   * [-] cosmic measurement 200MeV; warm or cold? (23.09.)
-  * [ ] build cable pocket (23.09.)+  * [x] build cable pocket (23.09.) 
 +  * [ ] VLAN commissioning (L) (24.09.)
   * [x] test run with stapler   * [x] test run with stapler
-  * [ ] Get cabled detector ready for movement (24.09.) +  * [x] Get cabled detector ready for movement (24.09.) 
-  * [ ] get chiller ready (27.09.) +  * [x] get racks ready (25.09.) 
-  * [ ] get racks ready (25.09.)+  * [x] get chiller ready (27.09.)
  
  
 Time plan in A1-hall: Time plan in A1-hall:
  
-  * [x] Move spectrometers (30.08.) +  * [x] move spectrometers (30.08.) 
-  * [x] Clear stuff in A1 hall (S) (30.08.) +  * [x] clear stuff in A1 hall (S) (30.08.) 
-  * [x] Disassemble exit beam pipe (29.08. 10 o'clock) +  * [x] disassemble exit beam pipe (29.08. 10 o'clock) 
-  * [x] Disassemble target chamber (06.09.) +  * [x] disassemble target chamber (06.09.) 
-  * [x] Build, install and measure target ladder+  * [x] build, install and measure target ladder
   * [x] install new target chamber    * [x] install new target chamber 
-  * [x] Build MayTech table in A1-Hall (10.09.) +  * [x] build MayTech table in A1-Hall (10.09.) 
-  * [ ] Build detector frame and adjust feet (24.09.) +  * [x] close target chamber and vacuum test (24.09.) 
-  * [ ] Move calorimeter to A1-Hall (25.09.) +  * [xbuild detector frame and adjust feet (24.09.) 
-  * [ ] Install calorimeter with exit beam pipe (25.09.) +  * [xmove calorimeter to A1-Hall (25.09.) 
-  * [x] Close target chamber and vacuum test (24.09.) +  * [xinstall calorimeter with exit beam pipe (25.09.) 
-  * [ ] Install infrastructure (PC, Racks, etc.) (26.09.) +  * [x] Install infrastructure (PC, Racks, etc.) (26.09.) 
-  * [ ] cable calormeter on rack side (priority: signal cables and LV, then: light pulser and HV) (27.09.) +  * [ ] cable calorimeter on rack side (priority: signal cables and LV, then: light pulser and HV) (04.10.) 
-  * [ ] Align and measure calorimeter (02.10.) +  * [ ] install chiller and dry air (04.10.) 
-  * [ ] install VAT and window and flange (09.10.)+  * [ ] build lead wall for chiller (11.10) 
 +  * [ ] biuld holding structure for VAT valve 
 +  * [ ] scintillator-pmt readout with VME crate  
 +  * [ ] holding structure for PMTs 
 +  * [ ] align and measure calorimeter (02.10.)
   * [ ] read out and control whole detector at once (04.10.)   * [ ] read out and control whole detector at once (04.10.)
-  * [ ] Cool detector (04.10.) +  * [ ] cool detector (07.10.) 
-  * [ ] Vacuum test of exit beampipe ? +  * [ ] install VAT and window and flange (09.10.) 
-  * [ ] Put vacuum on exit beampipe for beamtime (14.10.) +  * [ ] vacuum test of exit beampipe ? 
-  * [ ] Cosmic measurement, 25 MeV, cold (16.10.)+  * [ ] put vacuum on exit beampipe for beamtime (14.10.) 
 +  * [ ] cosmic measurement, 25 MeV, cold (16.10.)
   * [ ] install more nests, which are visible from the sides ?   * [ ] install more nests, which are visible from the sides ?
 +
 +Scintillators:
 +  * [ ] find 6 scintillators with PMTs
 +  * [ ] HV with VME crate
 +  * [ ] read out signal with VME crate (which module?)
 +  * [ ] holding structure
  
 Counting room: Counting room: