Line 10: | Line 10: | ||
* [x] leakage test, test at room temperature (J+P) (06.09.) | * [x] leakage test, test at room temperature (J+P) (06.09.) | ||
* [x] splitter board test (L) (06.09.) | * [x] splitter board test (L) (06.09.) | ||
- | * [ ] VLAN commissioning (L) (24.09.) | ||
* [x] humidity test (J+P) (17.09.) | * [x] humidity test (J+P) (17.09.) | ||
* [x] cool the detector (18.09.) | * [x] cool the detector (18.09.) | ||
Line 19: | Line 18: | ||
* [-] read out and control whole detector at once (20.09.) | * [-] read out and control whole detector at once (20.09.) | ||
* [-] cosmic measurement 200MeV; warm or cold? (23.09.) | * [-] cosmic measurement 200MeV; warm or cold? (23.09.) | ||
- | * [ ] build cable pocket (23.09.) | + | * [x] build cable pocket (23.09.) |
+ | * [ ] VLAN commissioning (L) (24.09.) | ||
* [x] test run with stapler | * [x] test run with stapler | ||
- | * [ ] Get cabled detector ready for movement (24.09.) | + | * [x] Get cabled detector ready for movement (24.09.) |
- | * [ ] get chiller | + | * [x] get racks ready (25.09.) |
- | * [ ] get racks ready (25.09.) | + | * [x] get chiller |
Time plan in A1-hall: | Time plan in A1-hall: | ||
- | * [x] Move spectrometers (30.08.) | + | * [x] move spectrometers (30.08.) |
- | * [x] Clear stuff in A1 hall (S) (30.08.) | + | * [x] clear stuff in A1 hall (S) (30.08.) |
- | * [x] Disassemble | + | * [x] disassemble |
- | * [x] Disassemble | + | * [x] disassemble |
- | * [x] Build, install and measure target ladder | + | * [x] build, install and measure target ladder |
* [x] install new target chamber | * [x] install new target chamber | ||
- | * [x] Build MayTech table in A1-Hall (10.09.) | + | * [x] build MayTech table in A1-Hall (10.09.) |
- | * [ ] Build detector frame and adjust feet (24.09.) | + | * [x] close target chamber and vacuum test (24.09.) |
- | * [ ] Move calorimeter to A1-Hall (25.09.) | + | * [x] build detector frame and adjust feet (24.09.) |
- | * [ ] Install | + | * [x] move calorimeter to A1-Hall (25.09.) |
- | * [x] Close target chamber and vacuum test (24.09.) | + | * [x] install |
- | * [ ] Install infrastructure (PC, Racks, etc.) (26.09.) | + | * [x] Install infrastructure (PC, Racks, etc.) (26.09.) |
- | * [ ] cable calormeter | + | * [ ] cable calorimeter |
- | * [ ] Align and measure calorimeter | + | * [ ] install chiller |
- | * [ ] install | + | * [ ] build lead wall for chiller (11.10) |
+ | * [ ] biuld holding structure for VAT valve | ||
+ | * [ ] scintillator-pmt readout with VME crate | ||
+ | * [ ] holding structure for PMTs | ||
+ | * [ ] align and measure calorimeter | ||
* [ ] read out and control whole detector at once (04.10.) | * [ ] read out and control whole detector at once (04.10.) | ||
- | * [ ] Cool detector (04.10.) | + | * [ ] cool detector (07.10.) |
- | * [ ] Vacuum | + | * [ ] install VAT and window and flange (09.10.) |
- | * [ ] Put vacuum on exit beampipe for beamtime (14.10.) | + | * [ ] vacuum |
- | * [ ] Cosmic | + | * [ ] put vacuum on exit beampipe for beamtime (14.10.) |
+ | * [ ] cosmic | ||
* [ ] install more nests, which are visible from the sides ? | * [ ] install more nests, which are visible from the sides ? | ||
+ | |||
+ | Scintillators: | ||
+ | * [ ] find 6 scintillators with PMTs | ||
+ | * [ ] HV with VME crate | ||
+ | * [ ] read out signal with VME crate (which module?) | ||
+ | * [ ] holding structure | ||
Counting room: | Counting room: |
beamtimes/2024/timeplan.1727096128.txt.gz · Last modified: 2024/09/23 12:55 by himuser