User Tools

Site Tools


beamtimes:2024:timeplan

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revisionPrevious revision
Next revision
Previous revision
beamtimes:2024:timeplan [2024/09/04 08:45] himuserbeamtimes:2024:timeplan [2024/09/30 12:03] (current) himuser
Line 2: Line 2:
  
 The goal is to have a fully equipped and running detector in A1 at October **16th**. The goal is to have a fully equipped and running detector in A1 at October **16th**.
-== **Firs commissioning beam time: 16.10.-27.10.** ==+=== **First commissioning beam time: 16.10.-27.10.** ===
  
  
Line 8: Line 8:
   * [x] Cable the detector (P, C, S, Aj) (30.08.)   * [x] Cable the detector (P, C, S, Aj) (30.08.)
   * [x] detector submodule position measurement (P+C+S) (06.09.)   * [x] detector submodule position measurement (P+C+S) (06.09.)
-  * [ ] leakage test, humidity test at room temperature or 10 deg (J+P) (06.09.) +  * [x] leakage test, test at room temperature (J+P) (06.09.) 
-  * [ ] splitter board test (L) (06.09.) +  * [x] splitter board test (L) (06.09.) 
-  * [ ] VLAN commissioning (O) (06.09.)+  * [xhumidity test (J+P) (17.09.) 
 +  * [x] cool the detector (18.09.) 
 +  * [x] cable the rack (O+L) (18.09.)
   * [x] assemble SADC setup (O+A) (13.09.)   * [x] assemble SADC setup (O+A) (13.09.)
-  * [ ] read out whole detector at once (13.09.) +  * [x] HV control (18.09.) 
-  * [ ] cosmic measurement 200MeV; warm or cold? (13.09.) +  * [x] read out commercial sensors with keysight (20.09.) 
-  * [ ] build cable pocket  +  * [-] read out and control whole detector at once (20.09.) 
-  * [ ] install more nests, which are visible from the sides +  * [-] cosmic measurement 200MeV; warm or cold? (23.09.) 
-  * [ ] Get cabled detector ready for movement (16.09.)+  * [x] build cable pocket (23.09.) 
 +  * [ ] VLAN commissioning (L) (24.09.) 
 +  * [x] test run with stapler 
 +  * [x] Get cabled detector ready for movement (24.09.) 
 +  * [x] get racks ready (25.09.) 
 +  * [x] get chiller ready (27.09.)
  
  
 Time plan in A1-hall: Time plan in A1-hall:
  
-  * [x] Move spectrometers (30.08.) +  * [x] move spectrometers (30.08.) 
-  * [x] Clear stuff in A1 hall (S) (30.08.) +  * [x] clear stuff in A1 hall (S) (30.08.) 
-  * [x] Disassemble exit beam pipe (29.08. 10 o'clock) +  * [x] disassemble exit beam pipe (29.08. 10 o'clock) 
-  * [x] Disassemble target chamber (06.09.) +  * [x] disassemble target chamber (06.09.) 
-  * [x] Build, install and measure target ladder+  * [x] build, install and measure target ladder
   * [x] install new target chamber    * [x] install new target chamber 
-  * [ ] Build MayTech table in A1-Hall (10.09.) +  * [xbuild MayTech table in A1-Hall (10.09.) 
-  * [ ] Move calorimeter to A1-Hall (17.09.) +  * [xclose target chamber and vacuum test (24.09.) 
-  * [ ] Close target chamber and vacuum test (20.09.) +  * [x] build detector frame and adjust feet (24.09.) 
-  * [ ] Install calorimeter (17.09.) +  * [x] move calorimeter to A1-Hall (25.09.) 
-  * [ ] Align and measure calorimeter (20.09.) +  * [xinstall calorimeter with exit beam pipe (25.09.) 
-  * [ ] Install exit beam pipe (04.10.) +  * [x] Install infrastructure (PC, Racks, etc.) (26.09.) 
-  * [ ] Vacuum test of exit beampipe  +  * [ ] cable calorimeter on rack side (priority: signal cables and LV, then: light pulser and HV) (04.10.) 
-  * [ ] Install infrastructure (PC, Racks, etc.) (04.10.) +  * [ ] install chiller and dry air (04.10.) 
-  * [ ] Cable calorimeter on Rack side (04.10.) +  * [ ] build lead wall for chiller (11.10) 
-  * [ ] Test all submodules (11.10.) +  * [ ] biuld holding structure for VAT valve 
-  * [ ] Put vacuum on exit beampipe for beamtime (14.10.) +  * [ ] scintillator-pmt readout with VME crate  
-  * [ ] Cool detector (14.10.) +  * [ ] holding structure for PMTs 
-  * [ ] Cosmic measurement25 MeV, cold+  * [ ] align and measure calorimeter (02.10.) 
 +  * [ ] read out and control whole detector at once (04.10.) 
 +  * [ ] cool detector (07.10.) 
 +  * [ ] install VAT and window and flange (09.10.) 
 +  * [ ] vacuum test of exit beampipe ? 
 +  * [ ] put vacuum on exit beampipe for beamtime (14.10.) 
 +  * [ ] cosmic measurement, 25 MeV, cold (16.10.) 
 +  * [ ] install more nestswhich are visible from the sides ? 
 + 
 +Scintillators: 
 +  * [ ] find 6 scintillators with PMTs 
 +  * [ ] HV with VME crate 
 +  * [ ] read out signal with VME crate (which module?) 
 +  * [ ] holding structure 
 + 
 +Counting room: 
 +  * [ ] network 
 +  * [ ] server 
 +  * [ ] computers etc.
  
 Cooling (J): Cooling (J):
-  * [ ] connect outer cooling (06.09.)+  * [x] connect outer cooling (06.09.)
   * [x] prepare manifold boxes   * [x] prepare manifold boxes
-  * [ ] humidity readout+  * [x] humidity readout (10.09.)
  
 Parts Missing: Parts Missing:
-  * temperature cables external +  * VAT holding structure 
-  * adapter plates for table (feetrails, etc.) +  * scintillatorsread out by PMTs; up to six
-  * "Belegbretter" for table +
-  * finish flange for exit beam pipe downstream +
-  * central alignment piece for calorimeter+
beamtimes/2024/timeplan.1725439503.txt.gz · Last modified: 2024/09/04 08:45 by himuser

Donate Powered by PHP Valid HTML5 Valid CSS Driven by DokuWiki