 ====== Timeplan for Setup in the A1-Hall ====== ====== Timeplan for Setup in the A1-Hall ======
  
-The goal is to have a fully equipped and running detector in A1 at October 18th.+The goal is to have a fully equipped and running detector in A1 at October **16th**. 
 +=== **First commissioning beam time: 16.10.-27.10.** === 
  
 To do in HIM hall: To do in HIM hall:
   * [x] Cable the detector (P, C, S, Aj) (30.08.)   * [x] Cable the detector (P, C, S, Aj) (30.08.)
   * [x] detector submodule position measurement (P+C+S) (06.09.)   * [x] detector submodule position measurement (P+C+S) (06.09.)
-  * [ ] leakage test, humidity test at room temperature or 10 deg (J+P) (06.09.) +  * [x] leakage test, test at room temperature (J+P) (06.09.) 
-  * [ ] splitter board test (L) (06.09.) +  * [x] splitter board test (L) (06.09.) 
-  * [ ] VLAN commissioning (O) (06.09.)+  * [xhumidity test (J+P) (17.09.) 
 +  * [x] cool the detector (18.09.) 
 +  * [x] cable the rack (O+L) (18.09.)
   * [x] assemble SADC setup (O+A) (13.09.)   * [x] assemble SADC setup (O+A) (13.09.)
-  * [ ] read out whole detector at once (13.09.) +  * [x] HV control (18.09.) 
-  * [ ] cosmic measurement 200MeV; warm or cold? (13.09.) +  * [x] read out commercial sensors with keysight (20.09.) 
-  * [ ] Get cabled detector ready for movement (16.09.)+  * [-] read out and control whole detector at once (20.09.) 
 +  * [-] cosmic measurement 200MeV; warm or cold? (23.09.) 
 +  * [x] build cable pocket (23.09.) 
 +  * [ ] VLAN commissioning (L) (24.09.) 
 +  * [x] test run with stapler 
 +  * [x] Get cabled detector ready for movement (24.09.) 
 +  * [x] get racks ready (25.09.) 
 +  * [x] get chiller ready (27.09.)
  
  
 Time plan in A1-hall: Time plan in A1-hall:
  
-  * [x] Move spectrometers (30.08.) +  * [x] move spectrometers (30.08.) 
-  * [x] Clear stuff in A1 hall (S) (30.08.) +  * [x] clear stuff in A1 hall (S) (30.08.) 
-  * [x] Disassemble exit beam pipe (29.08. 10 o'clock) +  * [x] disassemble exit beam pipe (29.08. 10 o'clock) 
-  * [x] Disassemble target chamber (06.09.) +  * [x] disassemble target chamber (06.09.) 
-  * [x] Build, install and measure target ladder+  * [x] build, install and measure target ladder
   * [x] install new target chamber    * [x] install new target chamber 
-  * [ ] Build MayTech table in A1-Hall (10.09.) +  * [xbuild MayTech table in A1-Hall (10.09.) 
-  * [ ] Move calorimeter to A1-Hall (20.09.) +  * [xclose target chamber and vacuum test (24.09.) 
-  * [ ] Close target chamber and vacuum test (20.09.) +  * [xbuild detector frame and adjust feet (24.09.) 
-  * [ ] Install calorimeter (27.09.) +  * [xmove calorimeter to A1-Hall (25.09.) 
-  * [ ] Install exit beam pipe +  * [xinstall calorimeter with exit beam pipe (25.09.) 
-  * [ ] Vacuum test of exit beampipe  +  * [x] Install infrastructure (PC, Racks, etc.) (26.09.) 
-  * [ ] Install infrastructure (PC, Racks, etc.) (04.10.) +  * [ ] cable calorimeter on rack side (priority: signal cables and LV, then: light pulser and HV) (04.10.) 
-  * [ ] Cable calorimeter on Rack side (04.10.) +  * [ ] install chiller and dry air (04.10.) 
-  * [ ] Test all submodules (11.10.) +  * [ ] build lead wall for chiller (11.10) 
-  * [ ] Put vacuum on exit beampipe for beamtime (18.10.) +  * [ ] biuld holding structure for VAT valve 
-  * [ ] Cool detector (18.10.) +  * [ ] scintillator-pmt readout with VME crate  
-  * [ ] Cosmic measurement, 25 MeV, cold+  * [ ] holding structure for PMTs 
 +  * [ ] align and measure calorimeter (02.10.) 
 +  * [ ] read out and control whole detector at once (04.10.) 
 +  * [ ] cool detector (07.10.) 
 +  * [ ] install VAT and window and flange (09.10.) 
 +  * [ ] vacuum test of exit beampipe ? 
 +  * [ ] put vacuum on exit beampipe for beamtime (14.10.) 
 +  * [ ] cosmic measurement, 25 MeV, cold (16.10.) 
 +  * [ ] install more nests, which are visible from the sides ?
  
-Cooling (J)+Scintillators
-  * [ ] connect outer cooling (06.09.) +  * [ ] find 6 scintillators with PMTs 
-  * [ ] dry air module readout via LAN (Pierre) +  * [ ] HV with VME crate 
-  * [ ] prepare manifold boxes +  * [ ] read out signal with VME crate (which module?) 
-  * [ ] humidity readout+  * [ ] holding structure
  
-What else+Counting room
-  * detector position measurement in A1 hall +  * [ ] network 
-  * Vacuum tests+  * [ ] server 
 +  * [ ] computers etc. 
 + 
 +Cooling (J): 
 +  * [x] connect outer cooling (06.09.) 
 +  * [x] prepare manifold boxes 
 +  * [x] humidity readout (10.09.)
  
 Parts Missing: Parts Missing:
-  * temperature cables extern +  * VAT holding structure 
-  * USBC cables for half subunits +  * scintillatorsread out by PMTs; up to six
-  * adapter plates for table (feetrails, etc.) +
-  * "Belegbretter" for table +
-  * finish flange for exit beam pipe downstream+